General Secretary Xi has delivered report to the 19th National Congress on Wednesday. There are two strategic judgments pointed out in Xi’s report: “that socialism with Chinese characteristics has now entered a new era, and that the principal contradiction in society is between people’s ever-growing needs for a better life…
The China Import and Export Fair, also known as the Canton Fair, was established in the spring of 1957 and is held annually in Guangzhou during spring and autumn. It is the most historic, largest, and most reputable comprehensive international trade event in China.From October 15 to 16, 2017, the…
After undergoing strict inspection and careful packing, SME successfully and punctually shipped the fifth batch of rolling mill equipment on October 5th. This marked the completion of the first-phase preparations for SME’s 150,000 TPA rebar and wire rod project in Ethiopia. Meanwhile, on-site civil works are progressing smoothly.
Project Name: Ethiopia Steely Rebar and Wire Rod Production Line Product: Rebar Φ8mm ~ 32mm / Wire Rod Φ5.5,Φ6mm Production capacity: annual output of 180,000 tons Contract Type: Turnkey Key Advantages: Advanced Production Technology & Equipment The production line utilizes a full-line continuous rolling process to ensure high-quality output. The…
On August 28, the SME investment team was invited to Pakistan for market research. By visiting old customers, meeting new friends, and especially experiencing the Eid-ul-Azha festival, SME Group gained updated insights into Pakistan and its investment environment.
In June, the senior management team of SME visited project sites in Nigeria and Ethiopia to inspect installation progress of projects and extend greetings to the project staff.
On February 13th, 2017, the SME electrical team held a technical meeting with electrical engineers from Nigeria. Both parties reached a consensus on several electrical issues, laying a solid foundation for the next phase of the Nigerian project.
The RIGITEC seamless pipe production line in Brazil completed commissioning on January 17. It primarily produces 33.4-114.3mm seamless pipes, with an annual capacity of 50,000 tons.
Ethiopia Mekelle Factory and SME Group officially signed a contract on November 18 to build a 150,000-ton rolling line. A celebration feast was held afterward in Ethiopia. The two production lines we previously delivered have brought great economic benefits, earning us a good reputation in the country. As a result,…
Through a series of professional yet engaging discussions, SME secured a new turnkey contract for a rebar and wire rod project from Adama in Ethiopia on October 28th. The project has a designed annual capacity of 150,000 tons, mainly producing 8–32mm rebar and 5.5–6mm wire rod. As SME Group’s second…